THE GLOWING ORACLE | SHOW US THE BILL — REGIONAL CASE STUDY
Evidence snapshot: November 18, 2026. Stage: proposed 100 Water Street data center stalled by a citywide zoning restriction.
Chestnut River Power and Infrastructure discussed a roughly 20-MW data center at the former Hampden Papers complex, 100 Water Street, Holyoke. The concept drew attention to an important distinction: this was a private commercial proposal, separate from Holyoke’s existing Massachusetts Green High Performance Computing Center (MGHPCC).
Project status
In June 2026, Holyoke adopted an ordinance making data centers an impermissible use in city zoning districts, with a carveout allowing the established MGHPCC to continue under specified limits. The Water Street concept has not been shown in the records reviewed here to have received a permit or to remain an active application. A city-adopted ad hoc committee is studying potential data-center impacts, including electrical demand, water consumption, environmental effects, fiscal impacts and public safety.
Electricity: the 20-MW concept is not a service agreement
Local reporting described a proposed 20-MW facility and quoted its developer as expecting nearby hydropower to meet the project’s needs without a major municipal-utility impact. That is a developer statement, not a published interconnection study or tariff. No executed service agreement, hourly load forecast, peak-demand profile, utility-upgrade cost allocation or curtailment plan was identified. A nearby source of low-carbon electricity does not, by itself, establish available capacity or who pays for delivery infrastructure.
Water and wastewater
The public sources reviewed do not establish a cooling design, water source, annual withdrawal, consumptive use, wastewater pathway or drought plan for 100 Water Street. The project’s comparison to MGHPCC should not be treated as proof it would use the same technology or amount of water. Require a project-specific water balance and discharge review before assessing the footprint.
Noise and neighborhood exposure
No operating equipment or site acoustic measurements exist for this unbuilt proposal in the sources reviewed. Public concern and debate are documented, but they are not a finding of measured noise harm. Before any future proposal, the applicant would need to disclose cooling and backup equipment, construction schedule, generator testing, cumulative sound levels and the nearest residential receptors.
Show Us the Bill — evidence status
- Electricity and grid costs: Not documented — the 20-MW size and developer’s hydropower statement are not an executed utility plan.
- Cooling water and wastewater: Not documented — no site-specific volumes, source or discharge design identified.
- Noise and air: Not measurable for an unbuilt proposal — equipment schedule and operating model unavailable.
- Taxes, jobs and services: Promoted benefits remain projections; no approved project or enforceable agreement was identified.
- Approval: Stalled — a June zoning ordinance bars new data-center use in the city, subject to the existing-facility carveout; no Water Street permit was identified.
Sources
- Holyoke City Council, June 11, 2026 ordinance minutes (data-center zoning order and existing-facility discussion)
- Western Mass News, “Holyoke mayor signs data center ban into law,” June 18, 2026
- Western Mass News, “Proposed data center sparks controversy in Holyoke,” June 3, 2026
- WBUR, September 11, 2026 reporting on Holyoke’s existing MGHPCC and zoning carveout
- Holyoke City Council, October 20, 2026 agenda and recommendation for an ad hoc impact study


Leave a Reply