THE GLOWING ORACLE | SHOW US THE BILL — REGIONAL CASE STUDY
Evidence snapshot: November 22, 2026. Stage: fuel-cell construction reported complete and facility listed in service; separate data-center phase unverified.
The public record tells two different stories about New Britain’s Energy & Innovation Park. The 20 MW fuel-cell facility was reported complete in 2024 and appears on Bloom Energy’s 2026 list of facilities in service. The 44 MW computing center was a separate phase in the original site plan. The fuel-cell records do not show that the computing center was built or is operating.
What the official record says
Connecticut Siting Council Petition 1350 covered a 19.98 MW fuel-cell facility at Building 107, 480 Myrtle Street. It was approved in 2018 and reopened under Petition 1350A, with a decision in December 2021. On April 14, 2023, the Council approved a revision to 20.0 MW and 67 Bloom fuel-cell units in place of 74. In a June 18, 2024 letter, Generate’s counsel reported that construction finished June 17 and that energization was expected later that month. The letter does not establish when commercial operation began. The original petition’s site plan identifies the 44 MW high-performance computing center as a separate phase, outside the fuel-cell project.
Electricity: distinguish generation, connection and IT load
The 20.0 MW figure is the approved generating capacity, not an annual energy total. In its February 2026 filing to the Siting Council, Bloom lists EIP Investments LLC under Petition 1350A among existing generators in service. Its “Data on Energy Use” table reports approximately 38.8 GWh in 2024 and 160.9 GWh in 2025 for that entry. The filing does not specify where the energy was metered or whether the figures are gross or net. They are not evidence of data-center consumption, grid imports or exports, or lower electricity bills.
In May 2023, FERC accepted the revised grid connection agreement for the 20 MW fuel-cell plant (ER23-1479). Article 11 assigns connection costs to Generate NB Fuel Cells and requires it to fund network upgrades unless the transmission owner elects to fund them. The agreement does not show what was ultimately paid, how upgrade costs were ultimately allocated under the tariff, or whether retail rates changed. It covers the generator, not the proposed computing center.
Water and wastewater
The council petition concerns a fuel-cell CHP installation and associated equipment, while the municipal plan depicts a later computing center. The reviewed public sources do not establish current cooling design, water withdrawal, consumption, treatment or discharge for an operating data center at this address. Do not import water data from other New Britain facilities or assume the proposed campus phase was built.
Noise and air
Fuel cells, transformers, cooling equipment and backup systems can have different sound and emissions profiles. The records establish that the fuel-cell plant was reported in service, but they do not quantify current property-line sound, emissions or exposure. They also do not identify operating schedules or equipment for a verified data center at the site.
Show Us the Bill — evidence status
- Project stage: The 20.0 MW fuel-cell project was reported complete in June 2024 and listed in service by Bloom in February 2026. Construction and operation of the separate 44 MW computing phase remain unverified.
- Electricity: Bloom reports annual energy figures for the fuel-cell facility. The meter boundary, grid import and export totals, data-center consumption and cost allocation remain unverified.
- Water: No site-specific operating water balance for a data-center phase found.
- Noise and emissions: Current sound, emissions and exposure remain unverified.
- Fiscal and public benefits: Historic forecasts do not establish tax receipts, jobs, or lower rates.
Records to obtain next
Request current occupancy and use from the city; the final as-built documents and operating permits for the fuel-cell facility; the current Connecticut Siting Council compliance record; gas and electric meter data; any data-center construction or occupancy permits; cooling and water/sewer records; current air and sound monitoring; and tax-incentive, property assessment and employment records.
Sources
- Connecticut Siting Council, Petition No. 1350 (19.98-MW fuel-cell proposal and docket)
- Connecticut Siting Council, Petition No. 1350A (reopened proceeding and subsequent decision)
- Connecticut Siting Council, New Britain facility list and approval dates
- City of New Britain, Energy & Innovation Park site plan (historic proposal, including separate 44-MW computing phase)