Northborough, MA — Iron Mountain BOS-1: Capacity, Renewable Claims and Missing Impact Data

Conceptual data-center building near utility lines with renewable-energy imagery and unmeasured capacity.

THE GLOWING ORACLE | SHOW US THE BILL — REGIONAL CASE STUDY
Evidence snapshot: November 22, 2026. Facility stage: operating colocation data center.

Iron Mountain identifies its Boston (BOS-1) facility at 171 Bearfoot Road, Northborough. The company reports a 22,000-square-foot building and 3.6 MW potential capacity; those are operator facility specifications, not measured annual consumption or a local grid-cost study. Iron Mountain also markets the site as LEED Gold and 100% matched with renewable energy. Matching claims need their accounting boundary and do not establish hourly local generation.

Electricity

Iron Mountain’s BOS-1 specifications and FAQ identify National Grid as the utility and say the site currently offers 1.2 MW of critical power, with 3.6 MW of potential capacity. Neither number is measured draw. Site-level peak demand, annual MWh, hourly load, utility upgrades and who pays for them remain unverified. Any usage comparison should separate IT load from whole-building load.

Cooling water and wastewater

Iron Mountain describes BOS-1 as using a waterless cooling design. That is an operator disclosure about cooling, not a facility-wide water balance or proof of zero water use. The reviewed sources did not provide dated site totals for withdrawals, consumption or wastewater, or a baseline against which claimed savings could be checked.

Noise and backup generation

Northborough’s 2013 Zoning Board of Appeals decision, case 13-08, approved a phased design at 171–175 Bearfoot Road and required ambient sound studies before and after construction. The historical plan called for phased emergency generators and diesel storage subject to permit conditions. The reviewed records did not include either completed sound study, a current equipment inventory, generator run logs or evidence of as-built compliance. The case number gives the town a precise starting point for locating those records.

Show Us the Bill — evidence status

  • Facility and power: Iron Mountain lists 171 Bearfoot Road, 1.2 MW currently offered and 3.6 MW of potential critical power. Renewable matching is an operator claim; neither it nor the capacity figures establishes actual site load or grid costs.
  • Water: Operator-described waterless cooling; actual site water and wastewater volumes remain unverified.
  • Noise: Ambient studies were required by case 13-08. Completed studies and current measurements were not located.
  • Community ledger: BOS-1’s 5.77-acre parcel at 171 Bearfoot Road (028.0-0066-0000.0) had a final FY2026 real-estate assessment of $5,693,200. The June 2019 Planning Board minutes describe the lot division. The adjoining warehouse at 175 is a separate parcel and should not be counted in this assessment. Assessed value is not taxes paid, incentives, jobs, or attributable service costs.